Skip to main content

Renovation of LFO No.1 Storage Tank in Zwitina Power Plant

|
 
Offer No.G01/2011

in exchange for removing the damaged fuel tank and installing a new one with the same specifications
 

Fuel tank No. (1) in the Zwitina gas station, has a capacity of 15,000 cubic meters, which was established in 1993 and was hit during the occurrence of the revolution in 3/2011 by a shell…. Fire broke out as a result, causing damage to the upper part and the roof of the tank, its equipment and accessories, and the damage reached even the protective concrete wall.

 Project implementation stages:

1- Removing the remaining fuel in the tank
2- Removing the damaged tank
3- Detecting the concrete base
4- Design, supply and installation of the new tank with the same specifications as the previous tank
5- Tests and robbery

Leave a Reply

Your email address will not be published. Required fields are marked *

GESCO

The Global Electricity Services Company was established in 2001 with the aim of meeting the growing need in the energy sector, as the company’s scope of work includes the construction and maintenance of stations, water station analysis, and oil and gas projects.


© All rights reserved GESCO