Maintenance of Sea Water Inlet at North Benghazi Steam Power Station

completed

General Information

  • Responsible Department :
  • ● Water Treatment
  • Category:
    Steam generation power plants
  • Location:
    Benghazi

Scope of work

The maintenance of the seawater inlet to the North Benghazi station included the preparation and maintenance of (4) seawater filters, maintenance of filters No. 1 and filter No. 2, temporary maintenance to ensure their continuity of operation, maintenance of filters No. 1 and filter No. 2 and their introduction into service, starting to dismantle filter No. 3 and filter No. 4 During the supply period, maintenance of refinery No. 3 and refinery No. 4 and their introduction into service, and maintenance of (2) bridges Maintenance of bridge No. 1 Maintenance of bridge No. 2 The maintenance process was carried out in two phases, in the first phase quick and temporary maintenance of 2 filters (TBS 1 & 2 ) with operation monitoring to ensure the flow of seawater to the station’s systems without interruption, in the second phase, spare parts were supplied and the installation of filters (TBS 3&4) began with operation monitoring to ensure the flow of seawater to the station’s systems.
GESCO

The Global Electricity Services Company was established in 2001 with the aim of meeting the growing need in the energy sector, as the company’s scope of work includes the construction and maintenance of stations, water station analysis, and oil and gas projects.


© All rights reserved GESCO