Supply and installation of a 30/66KV voltage transformer in the warehouse of AL-Brega Company

completed

General Information

  • Responsible Department :
  • ● Electricity Systems
  • Location:
    Tubruq

Scope of work

In this project, a 30/66 KV transformer with a capacity of 5MVA was supplied and installed, and 6KV switchboards were replaced at the Brega warehouse.
GESCO

The Global Electricity Services Company was established in 2001 with the aim of meeting the growing need in the energy sector, as the company’s scope of work includes the construction and maintenance of stations, water station analysis, and oil and gas projects.