GESCO Projects and Activities
Maintenance of Power Transformers, Voltage 11/30 kV – Maintenance of Transformer No. (2) at Al-Khoms Steam station
completed
General Information
-
Responsible Department :
-
● Electricity Systems
-
Location:Alkhums
Scope of work
With reference to the contract concluded with the General Electricity Company, the engineering and technical cadres of the Global Electricity Services Company completed the maintenance work on Transformer No. (2) of the Al-Khums Station, as follows:
Cleaning works (cleaning the space around the transformer, cleaning the concrete transformer base, cleaning the transformer, cleaning the coolers, cleaning all valves and flanges, cleaning the feed transformer).
Dismantling works (discharging transformer oil, dismantling oil coolers, dismantling the extractor relay, dismantling all valves and connections, removing the cover of the electrical box from both sides, removing cables and insulators)
Installation works (installation of coolers and other accessories, installation of insulators)
Painting works (transformer body paint, coolant paint, cable entry, and exit boxes, paint all transformer accessories, paint the concrete base of the transformer, paint the feeder transformer, paint the wall of the station building from the transformer side)
Concrete works (restoration of the concrete base of the transformer, installation of a turn around the transformer, laying gravel around the transformer)
Electrical works (installation of LED flashes on transformers).